Summary
Leander approved the final tranche of its $72 million commitment to the Brushy Creek Regional Water Treatment expansion, raising regional capacity from 41.9 to 64.2 million gallons per day — the water supply behind the city's rapid growth.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 15, 2026.
Impact analysis
Adds $36.24 million in contract revenue debt repaid through water system revenues; rates were locked in before the vote.
All Leander water customers, whose long-term supply security depends on the expanded treatment capacity.